As a PM, have you come across - “Shape up” & “Pitches”?
How are “Shape up” & “Pitch” different from “User stories” & “Agile”
In the recent startup I joined, we follow “Shape up” & “Pitch”. These 2 things are different from my past experiences — “Agile” & “User stories”.
Let’s see what they are all about.
Agenda:
- Shape up VS Agile
- Pitch VS User stories
- What do I like? and Why does Agile win?
- Why Shapeups if it lost against Agile?
Shape up VS Agile
Shape up
Shape-up is an 8-week cycle.
Deliverables come at the end of 8 week cycle.
The first 2 weeks of shapeup are about understanding the requirements (Pitch), grooming the requirements, fixing the scope, etc. Actual dev work starts in weeks 3,4,5,6 and QA starts in the 6 and 7th weeks, and the 7th and 8th weeks are for release and cool down.
Agile
Whereas Agile sprints can be a 2–4 weeks cycle. QA and launches come at the end of sprints. Grooming for the 10th sprint happens during the 9,8 or 7th sprints.